Roofing in Littleton: what Policy 20-005 requires

In Littleton, replacing 1 square (100 sq ft) or more of roof covering needs a permit, and the city counts small repairs together over any 365 days. Its roofing policy, #20-005, also requires an ice barrier at the eaves of every conditioned building, six nails per shingle, a mid-roof inspection, and the permit posted where it can be seen from the street. Starting without a permit or a Littleton contractor license adds an investigative fee equal to the permit cost.

Source: City of Littleton, Policy #20-005, Roof Covering and Installation Requirements (5/14/2020, 3rd rev. 6/12/2023), read 2026-10-20.

An independent publisher, not a roofing contractor. Facts last checked . How we source.

On this page
  1. Littleton's roofing rules at a glance
  2. The 1-square, 365-day threshold
  3. What Policy 20-005 requires on the roof
  4. The mid-roof inspection
  5. License and the investigative fee
  6. How Littleton differs from its neighbors
  7. Hail in Littleton's three counties
  8. What to ask a roofer in Littleton
  9. Common questions

Littleton's roofing rules at a glance

City of Littleton residential roofing rules (Policy #20-005, 3rd revision 12 June 2023)
TopicRule
Permit triggerPermit for 1 square (100 sq ft) or more in aggregate; up to 100 sq ft in any 365 days is a repair
Ice barrierRequired: ASTM D1970 ice barrier at least 2 ft inside the exterior wall line at the eaves of all conditioned structures
InspectionMid-roof inspection at 25–75% of covering installed with all underlayment and flashing in place; pre-roof inspections no longer required
DeckSpaced-board decks with gaps over 1/2 in need a 3/8 in (minimum) panel overlay and a sheathing-nailing inspection
Fastening and flashingSix nails per asphalt shingle minimum; galvanized drip edge
Permit displayPosted where it is visible from the street
ContractorValid City of Littleton contractor license required (class not named in the policy)

Littleton publishes its roofing rules as a single, dated policy, which makes them easy to quote back to a roofer. It was first issued on 14 May 2020 and revised for the third time on 12 June 2023.

The 1-square, 365-day threshold

Most metro cities set a repair threshold per job. Littleton's is different in two ways. First, the line is 1 square or more, so exactly 100 sq ft already needs a permit, where Thornton's "more than 1 square" would not. Second, the policy defines a repair as up to 100 sq ft in any 365 days, so it is cumulative.

Why it matters after hailA spring storm cracks 60 sq ft on the north slope; you repair it. A July storm damages another 60 sq ft. Together that is 120 sq ft within 365 days, which is over Littleton's repair allowance, so the second repair needs a permit even though each was small.

Use the permit checker with Littleton selected, and add up every repair from the past year before you enter the area.

What Policy 20-005 requires on the roof

Ice barrier on conditioned buildings

Littleton requires an ASTM D1970 self-adhering ice barrier at the eaves, extending at least 2 ft inside the exterior wall line, on all conditioned structures. That puts it with Centennial and against Lakewood, Thornton and Denver's 2015 guideline, which do not require it. An unheated detached garage is not a conditioned structure; ask your roofer how the policy applies to yours.

Six nails per shingle

The policy sets six nails per asphalt shingle as a minimum. Check that the shingle on your quote is installed to its maker's instructions as well; where those ask for more, the higher requirement applies.

Spaced-board decks

Older homes often have plank (spaced-board) sheathing. Where the gaps exceed 1/2 in, the policy requires an overlay of at least 3/8 in panels and a sheathing-nailing inspection before the roof goes on. If your house predates plywood decking, ask whether the quote includes this overlay, because it can only be found on tear-off.

Drip edge

Galvanized drip edge is required. It protects the deck edge and fascia from the water that runs off the shingles.

The mid-roof inspection

  1. Permit postedVisible from the street before work starts.
  2. Tear-off and deckOverlay and sheathing-nailing inspection if boards are spaced over 1/2 in.
  3. Mid-roofAll underlayment, ice barrier and flashing on; 25–75% of the covering installed.
  4. FinalRoof complete; permit closed.

Pre-roof inspections are no longer required, so the mid-roof visit is the only time an inspector sees the ice barrier and underlayment. The policy also requires a ladder extending 3 ft above the eave for the inspector. Ask your roofer to photograph the ice barrier and nailing at mid-roof and send you the photos.

License and the investigative fee

Colorado does not license roofers at the state level, so a roofer working in Littleton needs a valid City of Littleton contractor license, whatever licenses it holds in Denver or Aurora. If work starts without a permit or without that license, the city adds an investigative fee equal to the permit cost, and it may issue a stop-work order or a summons.

The fee is charged on the permit, which in practice means the property. Make the roofer's Littleton license number and the permit number part of the written contract that C.R.S. 6-22-103 already requires, and check both before the tear-off. License classes across the metro are on roofing licenses in the Denver metro.

How Littleton differs from its neighbors

Littleton against nearby cities (each from the city's own document)
RuleLittletonCentennialLakewood
Repair without permitUnder 100 sq ft, counted over 365 daysUnder 100 sq ftUnder 100 sq ft
Ice barrierRequired (conditioned buildings)Required on all roofsNot required
Mid-roof inspectionYes, in personYes, every reroofPhotos; none for asphalt shingles

The full five-city comparison, with Denver and Thornton, is in the permits guide.

Hail in Littleton's three counties

Littleton's city limits cross Arapahoe, Jefferson and Douglas counties. NOAA's Storm Events Database lists 158 hail reports in Arapahoe, 151 in Jefferson and 142 in Douglas County for 2016–2025; reports are county-level, so these are not Littleton-only counts.

Arapahoe County hail reports per year, 2016–2025
Arapahoe County hail reports per year, 2016–2025 2016: 8; 2017: 4; 2018: 25; 2019: 28; 2020: 4; 2021: 12; 2022: 5; 2023: 44; 2024: 22; 2025: 6 012243648 2016 8 2017 4 2018 25 2019 28 2020 4 2021 12 2022 5 2023 44 2024 22 2025 6
Show the data as a table
YearReports
20168
20174
201825
201928
20204
202112
20225
202344
202422
20256
Jefferson County hail reports per year, 2016–2025
Jefferson County hail reports per year, 2016–2025 2016: 14; 2017: 20; 2018: 16; 2019: 15; 2020: 2; 2021: 15; 2022: 2; 2023: 46; 2024: 9; 2025: 12 012253750 2016 14 2017 20 2018 16 2019 15 2020 2 2021 15 2022 2 2023 46 2024 9 2025 12
Show the data as a table
YearReports
201614
201720
201816
201915
20202
202115
20222
202346
20249
202512
Douglas County hail reports per year, 2016–2025
Douglas County hail reports per year, 2016–2025 2016: 28; 2017: 5; 2018: 12; 2019: 22; 2020: 5; 2021: 18; 2022: 2; 2023: 36; 2024: 8; 2025: 6 010192939 2016 28 2017 5 2018 12 2019 22 2020 5 2021 18 2022 2 2023 36 2024 8 2025 6
Show the data as a table
YearReports
201628
20175
201812
201922
20205
202118
20222
202336
20248
20256

Counted by us from the NOAA NCEI Storm Events details files, retrieved 2026-10-20. Method on Denver metro hail history.

What to ask a roofer in Littleton

The questions below cover Littleton's own license, permit and inspection rules. Metro-wide answers on deductibles, permits and contracts are in the Denver roofing questions page.

  • What is your City of Littleton contractor license number?
  • Will the permit be posted where it is visible from the street before work starts?
  • Does the quote include ASTM D1970 ice barrier 2 ft inside the wall line, and six nails per shingle?
  • If the deck is spaced boards, is the 3/8 in overlay priced, or how will it be priced once found?
  • Will you send me photos from the mid-roof inspection and proof the final passed?

Common questions

Do I need a permit to repair my roof in Littleton?

Yes if you replace 1 square (100 sq ft) or more of roof covering in aggregate. Littleton's Policy 20-005 treats up to 100 sq ft in any 365 days as a repair, so several small repairs in a year can add up to a permit.

Does Littleton require ice and water shield?

Yes. Policy 20-005 requires an ASTM D1970 ice barrier extending at least 2 ft inside the exterior wall line at the eaves of all conditioned structures.

What happens if a roofer starts without a permit in Littleton?

The city adds an investigative fee equal to the permit cost when work starts without a permit or without a valid Littleton contractor license, and stop-work orders or a summons are possible.

Does Littleton still do pre-roof inspections?

No. Policy 20-005 says pre-roof inspections are no longer required. A mid-roof inspection is required at 25–75% of the covering installed, with all underlayment and flashing in place.

Get roofing quotes in the Denver metro

Free and no obligation. Tell us the job and ZIP; we check whether a partner roofer covers it before passing anything on.

Enter a Denver-metro ZIP (800–804). Outside that, we do not have a partner yet.
Please add your name.
A phone number is how the roofer reaches you.
Please add a working email.
Please add the street address for the job.
Get roofing quotes